Approximate bill of quantities
An approximate bill of quantities (sometimes referred to as a notional bill of quantities or provisional bill of quantities) can be used on projects where it is not possible to prepare a firm bill of quantities at the time of tendering.
Generally, the design will be relatively complete, but there is either insufficient time or information to determine the exact quantities and so a conventional bill of quantities cannot be prepared.
Tendering on the basis of an approximate bill of quantities can allow early selection of the contractor and so an early start on site. However, the approximate nature of the bill of quantities will tend to result in more variations during construction and so less price certainty when the investment decision is made. This means that even if it is not possible to determine exact quantities, it is sensible to try to ensure quantities are as accurate as possible.
Some contracts allow for re-measurement of approximate quantities (for example, this is common on cut-and-fill on roadworks). Here, quantities are simply revised and payments made accordingly without the need to instruct a variation.
If an approximate quantity turns out not to have been a realistic estimate of the quantity actually required, this may constitute a relevant event, giving rise to claims for an extension of time and loss and expense.
Approximate bills of quantities can also be used during the design process as a tool for controlling design costs (see approximate quantities cost plan below). They are then sometimes included in the tender documents as a guide with a caveat stating that responsibility for measuring quantities lies with the contractor, and drawings and specifications take priority over any description in the approximate bills.
An approximate quantities cost plan is, in effect, a priced approximate bill of quantities. It is a development of the elemental cost plan, but unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects) the approximate quantities cost plan is a first attempt to measure defined quantities from drawings.
It presents a more accurate picture of where costs are distributed, in particular it draws to the attention of designers those elements of the design that are standard and those that are not - and as a consequence may be more expensive. The approximate quantities cost plan should form a solid base for an effective value engineering exercise. From the point that the approximate quantities cost plan has been approved, cost control can be introduced by treating changes as if they are variations.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities vs approximate quantities cost plan.
- Approximate quantities cost plan.
- Bill of quantities.
- CAWS.
- Common mistakes in bill of quantities.
- Extension of time.
- Firm bill of quantities.
- Loss and expense.
- New Rules of Measurement.
- Packaging.
- Provisional sum.
- Relevant event.
- Standard Method of Measurement (SMM7).
- Types of bill of quantities.
- Unpriced bill.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.